German Unity Transport Project 8

 Nuremberg – Erfurt – Halle/Leipzig – Berlin

Three construction phases by 2017

The first construction phase was the provision of the electronic signalling sub-centres of Leipzig East and Leipzig Hauptbahnhof, which are among the most efficient electronic signalling centres ever built in Germany.

(Photo: DB AG)

The second construction phase, which started in 2009, involved the associated work on the Leipzig City Tunnel.

(Graphic: DB AG)

The third construction phase, integration of VDE 8.2 into the Leipzig hub and the upgrade of the Leipzig-Mockau – Leipzig Hauptbahnhof section, commenced in 2012, to ensure opening of the new VDE 8.2 line by 2015 and the VDE 8.1 line by 2017.

(Graphic: DB AG)

Completion of the project is planned for the following dates:

Project phases Section Completion
Draft and key planning   March 2012
Commissioning Site clearance work (four sets of points, OLE, cable duct systems) September 2013
Commissioning Rackwitzer Strasse/Parthe railway bridges  
  1st construction phase September 2013
  2nd construction phase September 2014
  3rd construction phase September 2015
Commissioning Platforms inc. station throat Probably December 2015